Engineering firms: when the client changes the scope
What to do when the client asks for extra work in the middle of an inspection: record it, quote it separately, wait for acceptance and only then add it to the project.
A scope change in an engineering firm is handled in four steps, in this order: write down what the client asked for, quote the extra work in a separate proposal, wait for the client to accept it, and only then add it to the project with its own tasks. The original proposal stays as it was. That way the extra work gets paid and nobody argues later about what was included.
The usual case shows up halfway through an inspection. The engineer is at the client's warehouse checking the roof that was contracted, and the maintenance manager asks him to look at the new mezzanine while he is there. The engineer looks, takes photos and, back at the office, spends two days on a check nobody quoted. At invoice time, the client remembers the mezzanine as a favor and the firm remembers two days of work.
Why scope changes get lost
There is rarely bad faith. The request is made out loud, on site or over the phone, and it ends up in one person's notebook. Whoever handles the commercial relationship does not hear about it until the hours show up, and by then the work is done. If there was no price before the work, charging for it afterwards is a negotiation the firm usually loses.
In an engineering firm the risk is higher because scope rests on technical assumptions. One condition that was not in the design basis is enough for the client to ask for something else, and the request usually makes sense. What fails is the route: the request goes from the client's mouth to the engineer's notebook and from there into work, without ever passing through a price.
How to handle a scope change in an engineering firm
1. Record the request where the project lives
In the client's project, the engineer leaves the request as a comment on the inspection task, with the photos attached. Task comments are internal, so the team discusses the impact without the client reading that conversation. If the request was made out loud, you can create a task for the person at the client who made it, for example "Confirm you want the mezzanine review". They get an email with a link to confirm it even without a portal account.
2. Quote it separately
The extra work goes in a new proposal, with its own lines, price and validity date. If it resembles what was already sold, you duplicate the accepted proposal and get a draft with its lines to adjust; the document the client approved stays untouched. You can also log the request as an opportunity in the pipeline, so whoever owns the account sees it on their list.
3. Wait for the client's yes
The client accepts or declines the proposal in their Client portal, and the decision is kept with their name, the date and the version they approved. If your firm wants a signature on the document, you send it from the proposal with E-signatures: the client signs from a link and, once they sign, the proposal is accepted.
4. Add the work to the project
With the acceptance in the client record, the project lead adds the new phase or tasks, each with its owner and date. It is the same thing the page from proposal to project describes: what was agreed is in writing before anyone does it.
Two ways to bill the extra work
If the change was quoted at a fixed price, the accepted proposal becomes an invoice with the same lines, taxes and discount, without typing them again.
If it was quoted by the hour, you mark the extra-work tasks as billable and give them an hourly rate. When you create the invoice from the project, AgentticCRM prepares a draft with the hours not yet billed, at their rate. Hours already billed are not charged again, and if you discard the draft they go back to pending. The tasks and time page explains it.
If the amount on an invoice already issued needs correcting later, you do it with a credit note. The accepted proposal is not rewritten.
What the CRM does not decide for you
Whether a small change is absorbed or charged is still a decision for the partners. Some clients are worth giving an hour to, and that is fine, as long as it is written down that it was a gift.
AgentticCRM does not check calculations, drawings or technical reports either. It is not design software, CAD or document control. It keeps who asked for what, what was quoted, what the client accepted and what was billed. The CRM for engineering firms page explains what it covers and what it does not.
If you want to see the rest of a firm's day run in this order, in a day with a CRM in an engineering firm we follow a fictional firm hour by hour. Video production companies have the same problem with extra versions, as we describe in production companies and AV integrators.
Frequently asked questions
Does every small change need a proposal?
No. You can set a threshold with your partners: below it, the project lead notes it on the task and handles it; above it, it gets quoted. What matters is that the request is written down in the project, whether it is charged or not.
Can I start the extra work before the client accepts?
The system does not stop you: you can create the tasks whenever you want. But if you start without an acceptance, getting paid for that work depends again on everyone's memory.
Does the client see the hours the team logs?
No. In their portal they see the progress of the project and its phases, what you marked as visible, the tasks you assigned to them and the shared files. Logged time, budget and rate are visible only to your team.